The Port of Newhaven is a busy commercial harbour on the mouth of the River Ouse, East Sussex, providing regular cross-channel connections for freight and passengers.
Beckett Rankine has a longstanding relationship with Newhaven Port Authority, providing design and management of key assets for decades.
As a result, we have had the opportunity to demonstrate a cross-section of our maritime engineering expertise through our work on quay walls, flood defences, jetties and linkspans.
We identified and managed repairs needed to extend this asset’s life, including replacing the bearings and steel beams that support the deck.
As Newhaven is a working port, it was vital that ferry services continued throughout the works. We produced designs that allowed for this and worked with the contractor to optimise the construction methodology.
In order to minimise disruption, we carried out trial runs of the construction process in between ferry services, at the beginning of the programme. The identified solution was to lift the linkspan on to temporary bearings so that work could progress on the permanent ones. Replacement of steelwork was timed and co-ordinated such that no ferry sailings were affected or cancelled. We monitored the bridge carefully throughout to check for movement and ensure the safety of all.
For safety reasons, during bad weather vehicle and passenger ferries have to turn 180° in a relatively narrow channel after loading and unloading.
A unique concept was designed and implemented by Beckett Rankine in 1991 – a large ‘turning plate’ was installed on the quay wall for the ferries to use as a buffer, allowing them to make contact with the structure and aid turning without damaging the existing quay wall or vessel. The structure consists of heavy steelwork that bears onto rubber fenders.
This original structure is reaching the end of its design life. As ferry vessel continue to increase in size, we are installing a new, larger turning plate that will allow modular replacement going forward.
Our strategy is to produce pre-fabricated modular units that can be assembled and lowered into place by crane, minimising the impact on port operations during the works.
The new turning plate is due to be installed in Autumn 2024.
The ‘Cut Out’ is a beach area at the mouth of the River Ouse that has experienced severe erosion in recent years, destabilising the beach slope and existing flood defences.
We are managing and designing works to install a new revetment, which will restore the beach to its original profile and provide protection from future erosion. We are managing contractors on site, who are re-profiling the beach, installing ground anchors, and laying flexible concrete mattress.